Select Board — June 8, 2026
The meeting was characterized by a high level of public interest and a spirited series of technical and logistical inquiries from both the board and the community.
Public impact
Eversource Substation Infrastructure
See more
The board and public discussed the necessity of the substation for long-term reliability and electrification, while expressing significant concerns regarding visual aesthetics, transformer noise, and environmental impacts on wetlands.
The board established its role in oversight and requested more detailed visual renderings and noise modeling.
A public hybrid meeting is scheduled for June 24th, and Eversource will continue engineering designs for the access road and noise/visual mitigation plans.
Topics discussed
▶ 00:00 Power Forecasting and Reliability
Discussion regarding how Eversource forecasts long-term energy needs, such as electrification and data centers, and how the new substation model will impact power outages.
See more
The board inquired about how Eversource anticipates future load increases from factors like electrification and potential data centers. There was also a specific concern regarding whether the transition to a four-substation model would reduce the frequency of power outages for Burlington residents.
Eversource representatives explained that they use actual customer applications for forecasting and that the new distribution lines and simulations are designed specifically to improve local reliability.
▶ 02:40 Visual and Noise Mitigation
Inquiries into how the substation and towers will be visually integrated into the landscape and whether operational noise will impact neighbors.
See more
Board members expressed concern over the visual impact of large towers and fencing, particularly in winter when trees are bare. They also asked about operational noise (humming) from transformers. A question was raised regarding whether the substation would produce a hum or significant noise once operational. Project representatives explained that while transformers do produce some low-level noise, a noise consultant is involved in the project.
Eversource noted they work with property owners on planting and are using noise consultants to model and mitigate potential sounds as part of their EFSB filing. The project team will use existing background noise data and upcoming equipment specifications to model noise levels and determine if mitigation, such as fencing, is necessary.
Eversource will continue developing renderings and photo simulations to provide the community with better visual context. Noise modeling results and mitigation plans will be included in the filing to the EFSP.
▶ 05:02 Environmental Impact and Stormwater Management
Discussion regarding vegetation removal, wetland impacts, and the implementation of stormwater controls.
See more
The board raised concerns about the removal of over two acres of vegetation and changes to stormwater runoff. Questions were asked regarding existing contact with the town's conservation department.
Eversource confirmed they are incorporating a stormwater basin into the design and have been holding monthly meetings with the Planning Board and Conservation Agent.
Eversource will include stormwater permits and a Notice of Intent in their EFSB filing package.
▶ 09:59 Project Access and Community Engagement
Concerns regarding construction equipment access through residential streets and how the town will be notified of project updates.
See more
The board requested clarity on how large equipment (125-foot towers) would be transported to avoid blocking residential driveways. There was also concern that the community had not been adequately notified about the project. There was a clarification that an existing gravel access road exists, rather than a new one being built. The board discussed the road's location, its narrowness between houses, and whether it would require paving or regular maintenance like plowing. Representatives noted that once construction is complete, site access will be minimal as it is not a manned facility.
Eversource plans to use an existing access road via the water department near Mill Pond to avoid neighborhood streets. They outlined a multi-channel engagement strategy including mailers, library sessions, and a project website. The engineering and specific next steps for the road remain in flux and are still being worked through.
A public hybrid meeting is scheduled for June 24th from 6:00 PM to 8:00 PM. Continued engineering design for the access road.
▶ 1:01:49 Project Roles and Inter-departmental Coordination
Clarification of the responsibilities of the Select Board, DPW, and Conservation Commission regarding project permits and oversight.
See more
a speaker noted that the project documentation clarifies the roles of various town entities, such as the Select Board's involvement in grant allocation and the DPW/Conservation's roles in earth-moving and stormwater permits. A representative emphasized that while some permits are state-level, there will be active consultations with town administration and departments.
The board acknowledged their specific roles in the oversight and permitting process.
Active consultations between the project team and town departments (Select Board, DPW, etc.) will continue.
Controversy & dissent
Potentially controversial issues
Eversource Substation Project
Community vs. board tension
Action items
Notable statements
Anyone who sits at this table as a member of this board can't rubber stamp stuff. We have to ask the hard questions at every step along the way. — Unidentified speaker · Discussing the responsibility of the Select Board as the project progresses through various stages. ▶ 42:12
I just want to make it known that this isn't that... that is just, sort of, basic electrical infrastructure. We're not putting in a data center in Burlington, so people aren't gonna freak out about that. — Unidentified speaker · Clarifying to the public/board that the substation project is not a data center, despite recent public discourse. ▶ 25:14
I do wanna make it known that this isn't [a data center]... This is sort of just, basic electrical infrastructure. we're not putting in a data center in Burlington, so just, so people aren't, you know, freak out about that. — Unidentified speaker · Distinguishing the electrical substation project from recent public discourse regarding AI/data centers. ▶ 56:07
I just really wanna stress this is the beginning of a real, you know, public process and interaction. — Unidentified speaker · Acknowledging the Select Board's questions and emphasizing ongoing transparency. ▶ 1:01:13
Public comment
Accountability flags
Transcript vs. official minutes
Creating this report cost real money.
MeetingWatch attended, transcribed, and analyzed this meeting on its own dime. If this work is valuable to you, chip in to keep covering Burlington.
Follow Burlington
One email when a new report is published from the Select Board — or one weekly digest.
grok-4.3, gemma-4-26b, grok-4-fast, grok-4.20-0309-reasoning · analyzed 2026-06-10.