Infrastructure & Technology Committee — June 8, 2026

The meeting was a standard business session focused on infrastructure approvals with no public testimony or significant disagreement.

Date Monday, June 8, 2026 Duration 0.2h Speakers 5 Decisions 3 Routine

Public ⁠impact

Issues from this meeting with documented community impact.
01

Hazel CSO Sewer Separation and Water Main Improvements

$4.6 million infrastructure investment affecting drainage and water services. Affected: Residents in Ward 4 near the Broadway corridor.
See more
What was discussed

Public Works explained this is the second phase of the Broadway sewer separation project to address drainage issues. The scope includes replacing 4,000 feet of water main and addressing 120 lead services.

What happened

The committee approved the contract award to Performance Construction and Engineering LLC via a 4-0 vote.

What's next

Construction is expected to proceed following City Council approval, likely spanning the summer and fall.

other high impact
02

Richard Street, Robert Street, and North Russell Avenue Water Main Improvements

$3.18 million project involving water main replacement and 100 lead service replacements. Affected: Residents in the Ward 6 subdivision.
See more
What was discussed

The project aims to improve water efficiency for a specific subdivision. Discussion occurred regarding the bidding process and the use of the OpenGov platform to encourage competition.

What happened

The committee approved the contract award to Gerardi Sewer and Water Company via a 5-0 vote.

What's next

Work is expected to begin in late summer.

other high impact

Decisions ⁠logged

Every recorded vote, with timestamps and dissents.
Approval of Alderman's Resolution 26-03-51 (May 2026 meeting).
Motion by Alderman Larson, second by Alderwoman Baid.
4-0
Awarding the Hazel CSO sewer separation and water main improvements project (Resolution 26-03-28) to Performance Construction and Engineering LLC in the amount of $4,618,028.
Motion by Alderwoman Baid, second by Alderman Mesiacos.
4-0
Awarding the Richard Street, Robert Street, and North Russell Avenue water main improvements project (Resolution 26-03-44) to Gerardi Sewer and Water Company in the amount of $3,187,318.50.
Motion by Alderman Mesiacos, second by Alderman Larson.
5-0

Topics ⁠discussed

Click a topic to expand quotes and full context.
▶ 00:15 Approval of May 2026 Resolution

The committee reviewed and approved a resolution from the May 2026 meeting.

Speakers: Unidentified speaker
See more
What was discussed

The Chairperson requested approval for Alderman's Resolution 26-03-51, which originated from a meeting held in May 2026.

What happened

The resolution was approved via a 4-0 vote.

▶ 00:35 Hazel CSO Sewer Separation and Water Main Improvements

A resolution to award a $4.6 million contract for sewer separation and water main improvements in Ward 4 to Performance Construction and Engineering LLC.

Speakers: Unidentified speaker
See more
What was discussed

Kurt Muth (Public Works) explained this is the second phase of the Broadway sewer separation, addressing drainage in the corridor east of Broadway. The project includes replacing 4,000 feet of water main, addressing 120 lead services, and improving sanitary services. Committee members inquired about street closures, water shutdowns, and the contractor's familiarity with the city.

What happened

The resolution was approved via a 4-0 vote.

What's next

Construction is expected to proceed following City Council approval, likely spanning the summer and fall.

▶ 07:41 Richard Street, Robert Street, and North Russell Avenue Water Main Improvements

A resolution to award a $3.18 million contract for water main improvements in Ward 6 to Gerardi Sewer and Water Company.

Speakers: Unidentified speaker
See more
What was discussed

Public Works presented this as a major water main project targeting a subdivision to improve efficiency. The project involves replacing water mains and 100 lead services. Discussion centered on the lack of local bidders, with Public Works noting that larger projects often attract non-local contractors due to scheduling and scale.

What happened

The resolution was approved via a 5-0 vote.

What's next

Work is expected to begin in late summer.

Controversy & ⁠dissent

Where the board, the community, or the agenda diverged.

Potentially controversial issues

01

Richard Street, Robert Street, and North Russell Avenue Water Main Improvements

The project drew scrutiny regarding the lack of local contractors bidding on the $3.18 million contract, raising questions about whether the city's procurement process effectively supports local businesses.
Board position: The board supported the award to Gerardi Sewer and Water Company, accepting the explanation that large-scale projects often attract non-local firms.
low concern

Notable ⁠statements

The [Hazel CSO] project is essentially the second phase, the continuation of the Broadway sewer separation job we did last year. — Unidentified speaker · Describing the scope and history of the Ward 4 infrastructure project. ▶ 01:05
We used our OpenGov public bidding platform... I actually feel like we've gotten more bids since we started using that platform. — Unidentified speaker · Responding to concerns about the transparency and reach of the bidding process for the Ward 6 project. ▶ 11:06

Member ⁠positions

3 issues · 0 explicit · 11 inferred
Juany Garza
Chair
Present
Approval of May 2026 Resolution YES ~
Hazel CSO Sewer Separation and Water Main Improvements YES ~
Richard Street, Robert Street, and North Russell Avenue Water Main Improvements YES ~
Ted Mesiacos
Vice Chair
Present
Approval of May 2026 Resolution YES ~
Hazel CSO Sewer Separation and Water Main Improvements YES
Richard Street, Robert Street, and North Russell Avenue Water Main Improvements YES
Present
Approval of May 2026 Resolution YES ~
Hazel CSO Sewer Separation and Water Main Improvements YES ~
Richard Street, Robert Street, and North Russell Avenue Water Main Improvements YES ~
Shweta Baid
Member
Present
Approval of May 2026 Resolution YES
Hazel CSO Sewer Separation and Water Main Improvements YES
Richard Street, Robert Street, and North Russell Avenue Water Main Improvements YES ~
Keith Larson
Member
Present
Approval of May 2026 Resolution YES
Hazel CSO Sewer Separation and Water Main Improvements YES ~
Richard Street, Robert Street, and North Russell Avenue Water Main Improvements YES
Present
Approval of May 2026 Resolution YES ~
Hazel CSO Sewer Separation and Water Main Improvements YES ~
Richard Street, Robert Street, and North Russell Avenue Water Main Improvements YES ~

Positions marked ~ are inferred from context and may not reflect the member's explicitly stated position. UNCLEAR means the vote was split but the record did not name how this member voted — it is not a “yes.”

Public ⁠comment

What residents said — verbatim, with timestamps.
No public comments were identified in this meeting.
Support coverage

Creating this report cost ⁠real money.

MeetingWatch attended, transcribed, and analyzed this meeting on its own dime. If this work is valuable to you, chip in to keep covering Aurora.

Report composed by grok-4.3, gemma-4-26b, grok-4.20-0309-reasoning, grok-4-fast · analyzed 2026-06-09.